Mora-Dabanga-Kousseri Road: Works Progressing...
The joint efforts of the Somaf Group and Metag are bearing fruit, with a physical execution rate assessed at 5.28% as of September 30, 2026. The priority action undertaken on the ground consisted of securing user mobility, making a continuous 34-kilometer stretch between kilometer points 25 and 59 practicable, out of a total linear length of 41 kilometers.
Listen to the article
Click to generate the audio version
Ensuring transport fluidity despite the climatic constraints of the rainy season mobilizes all teams, while the upcoming installation of specific signage barriers must preserve the newly treated pavement layers.
The configuration of site installations is accelerating in parallel to provide an appropriate operational framework for technical teams and mission control experts. The complete clearing of rights-of-way frees up the necessary spaces for deploying key personnel required in the specifications, guaranteeing rigorous oversight of ongoing works. This human and material backbone constitutes the indispensable foundation for executing the planned engineering works and earthworks in subsequent phases.
Several major technical dossiers have been transmitted to supervisors for official validation to oversee the conformity of works. The calculation notes regarding pavement dimensioning, detailed platform studies, the environmental and social management plan, and the temporary signage system are currently undergoing thorough review. Coordinating these regulatory aspects with the effective progress of hydraulic works will enable the definitive pace of this highly anticipated reconstruction by local populations to be initiated.
Nlend Flore
Comments